What the Complete TABC Licensing Timeline Looks Like, From Strategy to Open Doors

On this page

TABC estimates about 30 to 35 days to process a license or permit once it has a complete application, and says some take longer. The weeks before that are set by deadlines in the Alcoholic Beverage Code: up to 30 days for each local certifying office, a mailed notice window of 14 to 7 days before filing, and, for new on-premise locations that need it, a sign that must be up for 60 days before the permit can issue. Where the sign applies, its 60 days are the floor, because no permit can issue before it has been up that long; the other clocks can run inside that period or, if started one after another, add months to it.

The phases and their clocks

Phase What happens Time set by law or TABC
1. Permit and location decision choose the permit, confirm the address is wet for it and clear of any local distance rule none; this is the applicant's work
2. 60-day sign on-premise applicants at a location not licensed for on-premises consumption in the prior two years post the sign at least 60 days before issuance; may start before the application is filed
3. Local and Comptroller certifications city secretary and county clerk certify or refuse; Comptroller signs the sales tax certificate up to 30 days for each local office after it receives the request
4. Notices newspaper publication in two consecutive issues where required; mailed notice to nearby residences for original on-premise applicants without an FB; written notice to nearby schools mailed notice 14 to 7 days before filing; school notice before filing
5. Filing complete application submitted through AIMS or on paper TABC's estimate starts when the application is complete
6. TABC review and issuance TABC processes the application and issues the license or permit about 30 to 35 days, sometimes longer

The two-month sign and the processing estimate overlap. A sign posted the day the location is secured can finish its 60 days during certification and TABC review, instead of adding two months at the end.

Where time is lost

  • Starting the sign late. Under Section 11.391 of the Alcoholic Beverage Code, the sign must be posted at least 60 days before the permit issues. TABC’s sign requirements page confirms the 60 days can begin before the application is submitted.
  • Requesting certifications after the application is otherwise done. Each local office’s 30 days begins when it receives the request, so a request made last adds up to a month after everything else is ready.
  • Missing the mailed-notice window. The mailed notice has to go out inside a fixed window before filing (Section 11.393), so a late mailing moves the filing date with it.
  • An incomplete file. TABC’s processing estimate on its license and permit FAQ runs from the date it receives a complete application; a request for missing information moves that date.

An example calendar

  1. Week 0. Secure the location, confirm its wet status and distance rules, and check TABC’s Public Inquiry System for any on-premise license at the address in the past two years to learn whether the 60-day sign applies.
  2. Week 0 to 1. Post the 60-day sign if required, request city and county certifications, and start the Comptroller’s sales tax permit.
  3. Weeks 1 to 5. Collect certifications, run the newspaper notice where the permit requires it, send school notices, and assemble ownership, lease, and financing documents.
  4. Filing week. Mail residential notices 14 to 7 days ahead, then file the complete application.
  5. After filing. Allow about 30 to 35 days for TABC, with the 60-day sign finishing its period in the same window.

A license or permit, once issued, is valid for two years and expires on the second anniversary of issuance, so the renewal date is set the day the permit issues.

This article is general information about Texas alcoholic beverage law, not legal advice, and reading it does not create an attorney-client relationship. Statutes and TABC rules change; confirm current requirements with the Texas Alcoholic Beverage Commission, the relevant city or county, or a licensed Texas attorney before acting.